Robotic Loading for a Stator Winding Section

A motor plant wants one operator to run several winding machines.

The challenge

  • Each winder needed its own operator for loading and unloading.
  • Night shifts were hard to staff.
  • Parts were damaged by manual handling.

Our solution

We placed a 6-axis robot between two winders and a stator tester. The robot picks bare stators from trays, loads the winders, moves wound stators to the tester and sorts OK and NG parts. One operator supplies trays and handles rejects.

What the project was designed to deliver

  • Fewer operators per winding section
  • Gentler, repeatable part handling
  • Stable output across all shifts
Project steps

How the project ran

1Cycle time study2Gripper designand trials3Cell layout andsafety design4Integration withexisting winders5Operator andmaintenancetraining

Example project: this page describes a typical requirement of this kind and how we solve it. Customer names and figures are not published. Ask us for reference projects and plant visits.

Have a similar project?

Tell us about your motor, output target and constraints. We will propose a solution and share relevant reference projects.